On Sunday, February 9, 2025, a fire broke out at a power grid substation in Gurugram at 8:40 am, triggering a 36-hour blackout across several sectors, impacting around 10,000 families. The fire severely damaged the 220kV substation in Sector 107, causing a significant loss estimated at ₹10-11 crore. The cause of the fire is under investigation by a high-level committee. Residents, relying on costly diesel generators, expressed frustration over the frequent power outages.

뉴스
A major fire broke out at the power grid substation in Gurugram on Sunday, February 9, 2025, at 8:40 am, leading to an extensive 36-hour blackout across several sectors. The fire affected at least 10,000 families in housing societies along the Dwarka Expressway, including sectors 99, 102, 103, 107, 108, and 109.
The fire caused severe damage to the 220kV substation in Sector 107, including the destruction of a set of 220/33kV transmission lines and the entire control panel. This damage has been estimated to result in a financial loss of approximately ₹10-11 crore, according to Haryana Vidyut Prasaran Nigam Limited (HVPN).
With no electricity, residents were forced to rely on diesel generators, which many considered both financially draining and harmful to the environment. One frustrated resident, Brigadier Anil Hooda (Retd.) from Sobha City in Sector 108, expressed his concerns about the long-term effects of these generators, which not only add to the pollution but are also costly for everyday use.
A high-level committee, led by a senior engineer, has been formed to investigate the cause of the fire. The investigation will determine if an operational failure, sudden power surge, or faulty equipment was the root cause. If substandard materials are found to have contributed to the incident, appropriate action will be taken against contractors.
This incident underscores the critical need for proactive monitoring and early detection systems in substations. Planck Vision Systems’ thermal imaging cameras provide 24/7 monitoring of substations, allowing operators to detect abnormal heat signatures before a fire becomes visible, preventing costly downtime and extensive damage. By constantly gathering data and analyzing trends, these cameras can ensure that substations are protected from unexpected failures, offering a valuable layer of safety.
변전소 모니터링을 위한 예측 유지보수
플랑크 비전 시스템 열화상 카메라는 24시간 연중무휴 모니터링을 통해 추세와 이상 징후를 식별하는 소프트웨어로 데이터를 지속적으로 수집하고 분석할 수 있습니다. 고정형 또는 팬/틸트 드라이브 카메라는 선명한 열화상 이미지로 변전소의 넓은 영역을 조사할 수 있습니다. 플랜크 비전 시스템 카메라는 항상 적시에 적재적소에 배치되어 예기치 않은 변전소 고장으로 인해 많은 비용이 발생할 수 있는 가능성을 제거합니다.