プランクビジョンシステムズは、以下のような業務用アプリケーションのポータブル検査および24時間365日モニタリング用の赤外線画像ソリューションを製造しています:早期火災検知、製造、変電所・トンネル、電気パネル・キャビネット、貯蔵施設、データセンター、体温上昇スクリーニングなどです。当社は、米国の赤外線センシング技術の中心地であるカリフォルニア州サンタバーバラに本社を置いています。2020年に設立された当社の設計チームは、15年以上にわたって赤外線/可視カメラシステムおよび現在世界中に流通している製品に携わってきました。当社は、お客様独自の赤外線イメージングニーズを満たすためにお客様と協力することを専門としています。 当社の実績あるシステムは、エネルギー生産・流通、食品生産、輸送、産業オートメーション、体温上昇(EBT)検出などの商業用途で世界的に設置されています。
Acting ZETDC Managing Director, Engineer Abel Gurupira explained what caused the Highfields Substation fire (Image: ZETDC/X)
WATCH: ZETDC Boss Explains What Caused Highfield Substation Fire
Acting Managing Director of the Zimbabwe Electricity Transmission and Distribution Company (ZETDC), Engineer Abel Gurupira, has shared what caused the fire that gutted the Highfield Substation on Sunday night.
The fire has left several areas, including Willowvale, Beatrice, Workington, and Glen Norah, without power.
Engineer Gurupira said the fire was triggered by a cable fault that got worse over time. He explained that an 11kv cable developed a problem a few days ago and was fixed by ZETDC. But shortly after repairs, the same cable developed another fault, which then spread to a transformer, causing it to catch fire.
“One of the cables that feeds these clients at 11kv faulted some time back, about three, four days before. This cable was repaired, and on successful repairing, as we tried to restore supplies to the rest of the clientele, there was another fault on the very same cable that occurred. Unfortunately, this fault then went all the way to the transformer, and the transformer caught fire. That’s precisely what caused the fire outbreak that we have seen on various platforms,” he explained.
Also read: Energy Minister July Moyo Updates on Hwange and Highfield Repairs: Here’s When Electricity Will Be Restored
Despite the damage, Gurupira said the system was built with backup capacity. While one of the substation’s transformers was destroyed, the second transformer remains in good condition. ZETDC expects to restore power to affected areas by Wednesday, 7 May.
“The good news is, we have our network in such a way that there’s some redundancy. Rather than one transformer, we have two transformers at that station. So, it’s only one transformer that got burnt down completely. The other one is healthy, and we are hoping that by tomorrow we will have restored that one,” he added.
Gurupira added that ZETDC is already supplying temporary power to some areas using other substations. Workington is being powered from the Kambuzuma substation, while Willowvale is receiving electricity from Parkridge.
“Again, we have other stations that are fed at 132kv to 33. 33kv lines that go to these stations, then enable us to backfeed the other clients that would ordinarily would have been fed from this particular station,” he explained.
Watch the video below:
Update from the ZETDC Managing Director (A), Engineer Abel Gurupira, at Highfield Substation with insights into the cause of the recent fire. #HighfieldFaultUpdate pic.twitter.com/U5o05JRW7g
— ZETDC (@ZetdcOfficial) May 5, 2025
Follow Us on Google News for Immediate Updates
Coming from a long line of television and radio personalities, it was only natural for Chris Matambanadzo to venture into the media space. Chris is an avid reader who fancies himself a philosopher and poet. He is passionate about anime, music and movies.
© 2023 iHarare – All Rights Reserved
© 2023 iHarare – All Rights Reserved
ソース
プランク・ビジョン・システムズは、以下のような業務用アプリケーションのポータブル検査および24時間365日モニタリング用の赤外線画像ソリューションを製造しています。