Planck Vision Systems manufactures thermal imaging solutions for portable inspection and 24/7 monitoring of commercial applications including: Early Fire Detection, Manufacturing, Substations & Tunnels, Electrical Panel/Cabinets, Storage Facilities, Data Centers and Elevated Body Temperature Screening. Our company is headquartered in Santa Barbara CA, the capital of infrared sensing technologies in the United States. Founded in 2020, our design team has worked together for more than 15 years on thermal/visible camera systems and on products that are currently distributed worldwide.We specialized in working with our customers to meet the unique thermal imaging needs of their clients. Our proven systems have been installed globally in commercial applications for energy production and distribution, food production, transportation, industrial automation, and elevated body temperature (EBT) detection.
The concept plan for the department of public works facility and fire substation.
The concept plan for the department of public works facility and fire substation.
The Finance Committee was given an opportunity to comment on the estimated cost of the proposed joint facility for the Department of Public Works (DPW) and fire substation during a meeting held on Tuesday, July 15.
The aging fire station, originally constructed in 1950, is outdated and, due to its proximity to the floodplain, is at risk of flooding during heavy storms and rising seas. The DPW facility, built in 1972, is also considered too small, run-down and past its useful lifespan. The current DPW facility does not meet safety code requirements.
The estimated cost to replace the facility is projected to be approximately $58.2 million and the current DPW location on Route 130 has been selected as the optimal location for the project.
As an alternative, Mike Richard of Weston & Sampson, the design firm for the project, said that the group looked at renovating the current structures.
Richard said that both buildings are “severely undersized” for current operations.
When it comes to the current fire station on Route 6A, Richard said that there is a Federal Emergency Management Agency (FEMA) flood elevation three feet above where the finished floor sits. However, he said that in order to meet code the building would have to be raised an additional two feet for a total of five feet.
He said that reusing both of the buildings would require replacement of most aspects of the structure. The main framing and portions of the foundations would be the main salvageable aspects of both buildings, with some additional work needed in order to meet the code.
Richard said that renovating the DPW building is projected to cost $7.6 million and renovations for the current fire station on Route 6A are projected to cost $17.3 million.
However, Richard said that renovating the buildings “really doesn’t address some of the shortcomings of the facility and the square footage requirements.”
Sitework for the proposed joint facility is expected to cost $9,926,000.
Richard said that 68% of the site work costs are general non-site-specific costs, totaling $6,177,507. The site-specific costs make up 32% of the site costs, totaling $2,080,862.
The site-specific costs include the retaining walls, import of fill and paving and curbing of the access road to Charles Street.
Soft costs for the site are expected to total at $12,257,000 and may include special geotechnical services to address the unsuitable soils identified on the site, and permitting and or design costs that may be associated with building adjacent to a landfill.
“Anybody that’s familiar with the site knows that it’s challenging, there are several access points going into the site, there are other uses on the site, and there’s a hill that slopes,” said Richard.
Multiple Finance Committee members noted the site-specific costs and had asked during prior meetings to include alternative sites for the project.
Richard presented two alternative site locations, 34 Quaker Meetinghouse Road and 269 Quaker Meetinghouse Road.
“Both these sites did involve some additional site specific site work to the point of $1.2 million. But it was also pointed out to us that if we were to relocate the public works facility we need to provide some additional support space for the landfill and transfer station attendants as well,” Richard said, adding that the estimated cost for the transfer station structure is between $1 million and $1.4 million.
“When you think about going to another site, particularly one of these two sites, what you’ll find is the cost savings is relatively minimal,” Richard said.
Town Manager George H. “Bud” Dunham said that the 269 Quaker Meetinghouse Road location, which is across from the Oak Ridge School, would likely include additional work installing traffic lights at the intersection.
Finance Committee member Nancy A. Crossman said that she felt that the alternative site plans were “skimmed over quite quickly.”
“Maybe having a light isn’t a bad thing because you are probably going to end up looking at maybe a light on [Route] 130,” she said. “We are looking at a huge increase in the taxes and most people say I can’t afford it, that’s the reality that has to be looked at regardless of the need and I think the need is there.”
Finance Committee member Kevin Klein asked DPW Director Paul S. Tilton if transfer station attendees would still be able to utilize the DPW building at the proposed site. Tilton said that yes, they would be able to continue utilizing DPW space.
Finance Committee member Bob J. Guerin asked if a “bare bones” version of the buildings could be explored.
Dunham said that the team can go back to explore those options.
Guerin also asked if the town could provide a list of other upcoming needs to help inform the decision.
Finance Committee member Matthew D. Anderson said that he was concerned that delaying the project would result in higher costs due to inflation over the years.
“I don’t see how we are doing the town a service, or the taxpayer a service by delaying to get more information to ultimately need to do something,” Anderson said. He added that Fire Chief John J. Burke has worked with the consultants to design a project that is essentially bare bones.
Select Board vice chairman Robert George made a number of suggestions to help cut costs down.
He recommended cutting down on costs in a number of line items, including replacing the old DPW building with the new one in the same spot, rather than putting it in the “hole” on the property; he said that this would result in about $10 million in savings.
He also suggested splitting the project because “people aren’t going to vote for it” adding that the power plant property could be a possible location for the fire substation.
The Finance Committee will continue the discussion on the project next month.
Your comment has been submitted.
Reported
There was a problem reporting this.
Log In
Keep it Clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
PLEASE TURN OFF YOUR CAPS LOCK.
Don't Threaten. Threats of harming another person will not be tolerated.
Be Truthful. Don't knowingly lie about anyone or anything.
Be Nice. No racism, sexism or any sort of -ism that is degrading to another person.
Be Proactive. Use the 'Report' link on each comment to let us know of abusive posts.
Share with Us. We'd love to hear eyewitness accounts, the history behind an article.
Your browser is out of date and potentially vulnerable to security risks.
We recommend switching to one of the following browsers:
Sorry, an error occurred.
Already Subscribed!
Cancel anytime
Account processing issue – the email address may already exist
A look back at what was making headlines years ago.
An e-newsletter with Bourne news sent each Wednesday.
Receive notices of breaking news for the Upper Cape.
An e-newsletter highlighting what’s going on at the Upper Cape schools.
An e-newsletter with Falmouth news sent each Tuesday.
A Monday morning e-newsletter with stories that readers might have overlooked in Friday’s editions and a roundup of the stories that attracted the most attention on the Enterprise’s website during the past week.
An e-newsletter with Mashpee news sent each Wednesday.
An e-newsletter with Sandwich news sent each Wednesday.
An e-newsletter sent on Thursdays highlighting local entertainment for the coming week.
A good news e-newsletter delivered every Saturday morning.
A Saturday afternoon newsletter highlighting sports from the Upper Cape towns.
A Friday e-newsletter with headlines from all four Upper Cape towns.
Sign up with
Thank you .
Your account has been registered, and you are now logged in.
Check your email for details.
Invalid password or account does not exist
Sign in with
Submitting this form below will send a message to your email with a link to change your password.
An email message containing instructions on how to reset your password has been sent to the email address listed on your account.
No promotional rates found.
Secure & Encrypted
Secure transaction. Secure transaction. Cancel anytime.
Thank you.
Your gift purchase was successful! Your purchase was successful, and you are now logged in.
A receipt was sent to your email.
source
Planck Vision Systems manufactures thermal imaging solutions for portable inspection and 24/7 monitoring of commercial applications including